Key events 2007 – 2017

2007

MAY

Samruk-Energy” joint-stock company was established

NOVEMBER

The first issue of shares was registered


2008

MAY

A decision to create and construct a Balkhash TPP with a design capacity of up to 4000 MW was made

NOVEMBER

95.8% of shares were transferred to «Sovereign Wealth Fund «SamrukKazyna» JSC, 4.2% of shares to «KazTransGas» JSC

DECEMBER

Acquisition of a 50% stake in Forum Muider, which owns 100% stake in the equity capital of “Bogatyr Komir” LLP


2009

The commissioning of 9 substations in Almaty, the capacity increase was 488 MVA

JULY

Acquisition of a 100% stake in the authorized capital of “Alatau Zharyk Company” JSC


2010

MAY

The commissioning of substations No.137А “Central“ (2nd stage) and “Sayran“ in Almaty city

NOVEMBER

The commissioning of “Novaya No.16” substation in Almaty region Putting facilities for reconstruction of substations “Beineu“, “Umirzak“ in Mangistau region into operation

DECEMBER

The commissioning of substations Medeu, Shymbulak, KazGU, Yermensay in Almaty


2011

APRIL - JUNE

Acquisition of 100% stake in the authorized capital of “SamrukEnergy Stroy Service” LLP

Acquisition of 50% stake in “Ekibastuz SDPP-1 named after Bolat Nurzhanov” LLP

Acquisition of a 100% stake in the authorized capital of “AlmatyEnergoSbyt” LLP

OCTOBER

Joining the UN Global Compact

DECEMBER

All common shares of “Samruk-Energy” JSC held by “KazTransGas” JSC were transferred to the trust management of “Samruk-Kazyna” Sovereign Wealth Fund” JSC

Acquisition of a 100% stake in equity capital of “Tegis Munay” LLP, which owns 100% of “Mangyshlak-Munay” LLP


2012

JANUARY

A decision to create “Samruk-Green Energy” LLP was taken

AUGUST

Acquisition of 43.65% stake in «Almaty Power Plants» JSC

OCTOBER

Acquisition of a 50% stake in “Ekibastuz SDPP-1 named after Bolat Nurzhanov” LLP

Acquisition of 100% of shares in the authorized capital of “First Wind Power Plant” LLP by “Samruk Green Energy” LLP

DECEMBER

Placement of the first Eurobonds on the Irish and Kazakhstan stock exchanges

Kensai substation with a 220 kV power line Kensai of CHP-3 in Almaty region was put into operation


2013

MARCH

3rd place in the nomination “The best employer company in “two capitals “of the Republican contest “Senim-2012”

AUGUST

The commissioning of “Mamyr” substation in Almaty region

DECEMBER

Commissioning of a 2 MW solar power plant in Kapshagai city Acquisition of a 100% interest in the authorized capital of “Kazhydrotechenergo” LLP

Putting into operation of Almaty CHP-2 III stage in Almaty city


2014

MAY

Commissioning of closed type “Esentai” substation


2015

AUGUST

Launch of the wind power plant “First Wind Power Plant” LLP Putting into operation “Besagash”, “Mamyr”, “Altay” substations in Almaty

DECEMBER

Receiving the Grand Prix of the President’s Prize “Paryz” 2015 World rating agency Standard & Poor’s confirmed the credit rating at the level of “BB”, short-term credit rating at the level of “B”. The outlook for the rating change is “Stable”


2016

APRIL

Opening of the Regional Dispatch Center in “Mangistau Distribution Power Grid Company” JSC

Resumption of electricity exports to Russia and Kyrgyz Republic

MAY

Commissioning of turbine unit No.3 of “Aktobe CHP” JSC

SEPTEMBER

Commissioning of boiler unit No. 8 of CHP-2 of “Almaty Power Plants” JSC

NOVEMBER

Upgrading of 500 kV outdoor switchgear at “Ekibastuz SDPP-1” LLP was completed